Projects Completed Oil, gas & petrochemicals
Saudi Aramco Master Gas System Expansion Phase II – Booster Gas Compression I, III & V
- End user
- Saudi Aramco
- Main contractor
- SEPCO Arabia Co.
- GVS role
- GVS as subcontractor
- Location
- Al Hassa, Khurais and Dhurma
- Date
- 15 March 2018
- Value (SAR)
- 13,315,121
Scope of work
Works across three booster gas compression stations.
Site preparation for temporary facilities at BGCS I, III and V; site preparation and development for main site construction; construction of the Saudi Aramco Project Management Team (SAPMT) camp and site offices; storm-water drainage and excavation of soil and rock; steel structure erection and welding; asphalt road works and pavement.
Project statuses and values are as recorded in the GVS company profile (December 2024) and may have changed since.

More projects
| Project | End user | Value (SAR) | Status |
|---|---|---|---|
| Civil development works – C3/C4 refrigeration units and storage tanksJuaymah NGL Plant · 10/03/2023 | Saudi Aramco | 10,300,000 | Completed |
| SCADA system installation at SAOO fields (65 well heads)Udhailiyah, Haradh · 15/11/2020 | Saudi Aramco | 3,630,000 | Completed |
| SADARA hydrogen peroxide – civil infrastructure packageJubail · 28/10/2018 | SADARA | 2,500,000 | Completed |