Projects Completed Infrastructure
Arar city sewer network – Phase 3B
- End user
- Ministry of Environment, Water & Agriculture
- Main contractor
- Gulf Refinery Trading & Contracting Co.
- GVS role
- GVS as subcontractor
- Location
- Arar
- Date
- 2019
- Value (SAR)
- 29,567,000
Scope of work
Sewer network and underground utilities using GRP pipes from 200 to 900 mm diameter.
Project statuses and values are as recorded in the GVS company profile (December 2024) and may have changed since.

More projects
| Project | End user | Value (SAR) | Status |
|---|---|---|---|
| General grading services for the industrial area – JazanJazan · 2023 | Royal Commission for Jubail and Yanbu | 19,700,895 | Completed |
| Reinforcement of community irrigation system, Phase IV (RC-575-C35)Jubail · 2021 | Royal Commission for Jubail and Yanbu | 20,451,668 | Completed |
| Warehouse leveling and concrete slabsJuaymah · 07/09/2024 | Saudi Aramco | 1,215,000 | In progress |